Construction Start
Construction Start
Construction Start
Construction and Geothermal Update
Site Work Start
Special Permit and Design Review of building and site plan.
325 Binney Street building design will be presented.
Presented the building design at a virtual ECPT meeting.
Cambridge City Council meeting where Grand Junction Pathway Overlay Zoning passed with a 9-0 affirmative vote.
325 Binney Street re-zoning presentation at the Ordinance Committee. Referred out of committee and back to the full council for consideration.
325 Binney Street rezoning presentation at the East Cambridge Planning Team meeting.
325 Binney Street re-zoning presentation at the Ordinance Committee.
325 Binney St rezoning presentation at the Planning Board. Positive recommendation granted by the Planning Board.
Third filing of the Grand Junction Pathway Overlay Rezoning Petition
Beginning in the Fall of 2018 and stretching through February 2020, we attended more than 30 community meetings to discuss revised plans for the project. Presentation included the Linden Park Neighborhood Association, East Cambridge Planning Team, Cambridge Redevelopment Authority and the East Cambridge Business Association.