Construction Update 11/19/2021

Neighbors,

The construction team for 325 Binney will be setting a large steel beam this weekend that will require a mobile crane and support vehicles. The work will take place between 9a and 4p on Saturday. The site will be closed for the Thanksgiving holiday next Thursday November 25th.

Site work hours are from 7a - 6p per the Cambridge Construction Ordinance.

Do not hesitate reaching out with any questions or concerns.

Happy Holidays

Construction Update 10/15/2021

The construction team for 325 Binney will be setting a second tower crane in place per the City approved Construction Management Plan.  This will be a 3 day delivery and installation process that necessitates a portion of Fulkerson St (between Bent and Binney Street) to be closed and traffic to be detoured one block east to Sixth Streets. The street detour and closure is being coordinated by the City of Cambridge Traffic & Parking Department. This is the same detour that was used for the initial tower crane delivery and installation in late August.

The street will be closed starting at 7am on October 27th and the detour will remain in place until 6pm on October 29th

Site work hours are from 7a - 6p per the Cambridge Construction Ordinance.

Do not hesitate reaching out with any questions or concerns.

Construction Update 10/6/2021

As part of the city approved Construction Management Plan for 325 Binney Street, pedestrians will be re-routed to the sidewalk on the north side of Binney Street from the One Kendall Square Parking Garage exit to Fulkerson Street. This sidewalk closure will be in effect from October 8, 2021 through January 31,2023. During this time pedestrians will be required to cross to the south side of Binney Street at the OKS Garage exit and will be able to cross back to the north side of the street at the Fulkerson Street intersection. The attached diagram provides a visual of the sidewalk closure with pedestrian rerouting. 

Please don’t hesitate reaching out with any questions.

Construction Update 9/22/2021

Hello neighbors,

Site work continues at 325 Binney Street with foundation installation and steel erection on-going. Geothermal well installation continues on schedule. The first tower crane is erected and the second tower crane is tentatively scheduled to be delivered and erected Wednesday October 27th through Friday October 29th. This will be a 3 day delivery and installation process that necessitates a portion of Fulkerson St (between Bent and Binney Street) to be closed and traffic to be detoured one block east to Sixth Streets. The street detour and closure is being coordinated by the City of Cambridge Traffic & Parking Department.

Site work hours are from 7a - 6p per the Cambridge Construction Ordinance.

Do not hesitate reaching out with any questions or concerns.

Construction Update 8/16/2021

Hello neighbors,

Site work continues at 325 Binney Street with foundation and wall installation on-going. Geothermal well installation has commenced. The first tower crane is scheduled to be delivered and erected Monday August 30 through Wednesday September 1st. This will be a 3 day delivery and installation process that necessitates a portion of Fulkerson St (between Bent and Binney Street) to be closed and traffic to be detoured one block east to Sixth Streets. The street detour and closure is being coordinated by the City of Cambridge Traffic & Parking Department.

Site work hours are from 7a - 6p per the Cambridge Construction Ordinance.

Do not hesitate reaching out with any questions or concerns.

Construction Update 7/22/2021

Hello neighbors,

Site work continues at 325 Binney Street with foundation and wall installation on-going. Geothermal test well program was successful and the full installation program will begin in early August. The first tower crane is scheduled to be delivered and erected the last week in August. This will be a 3-4 day delivery and installation process.

Site work hours are from 7a - 6p per the Cambridge Construction Ordinance.

Do not hesitate reaching out with any questions or concerns.

Construction Update 6/7/2021

Hello neighbors,

Site work continues at 325 Binney Street with excavation and wall installation on-going. Test geothermal wells will begin to be installed this week. The Virtual Mock Up installation has begun and will be completed by the end of June.

Site work hours are from 7a - 6p per the Cambridge Construction Ordinance.

Do not hesitate reaching out with any questions or concerns.

Construction Update 5/7/2021

Hello neighbors,

Site work continues at 325 Binney Street with excavation and wall installation on-going. Test geothermal wells will begin to be installed at the end of May. The Virtual Mock Up installation will begin in the coming weeks.

Site work hours are from 7a - 6p per the Cambridge Construction Ordinance.

Do not hesitate reaching out with any questions or concerns.

Construction Update 4/9/2021

Happy Spring everyone!

Site work continues at 325 Binney Street with excavation underway and wall installation on-going. Next week a crawler crane will be installed to assist with the wall installation. Concrete barriers will be moved into Fulkerson St for safety and access.

Site work hours are from 7a - 6p per the Cambridge Construction Ordinance.

Do not hesitate reaching out with any questions or concerns.

Construction Update 12/22/2020

Site work continues at 325 Binney Street with the sheeting installation more than half way complete. Site work and soil excavation is well underway.

Site work hours are from 7a - 6p per the Cambridge Construction Ordinance.

Christmas and New Years Day no work will be performed.

Happy New Year from the 325 Binney Street Team. Do not hesitate reaching out with any questions or concerns.

Site Work Update 11/13/2020

325 Binney Street site work has commenced and next week sheeting installation will begin. The work will start on the southwest corner of the site (near Binney St & railroad tracks) and will move in a clockwise direction around the site.

Site work hours are from 7a - 6p per the Cambridge Construction Ordinance.

Please do not hesitate reaching out with any questions or concerns. Thanks

Planning Board Oct 20

We will be presenting to the Cambridge Planning Board Tuesday October 20, 2020. Please join virtually to find out the latest about this project!

Join us online! Virtual Community Meeting on July 15th at 6:30PM!

We’ll be hosting a virtual meeting this coming Wednesday, July 15 to discuss 325 Binney Street building design.

Due to the current situation and limits on in-person gatherings, the meeting will take place online using Zoom. You can join us virtually by following the link: https://nbbj.zoom.us/j/94181215826

 or by dialing in to:

iPhone one-tap : US +12532158782,,94181215826#

or        

Meeting ID: 941 8121 5826                   

Join by phone:

       +1 312 626 6799US (Chicago)

       +1 646 876 9923US (New York)

       +1 301 715 8592US (Germantown)

       +1 408 638 0968US (San Jose)

       +1 669 900 6833US (San Jose)

       +1 253 215 8782US (Tacoma)

       +1 346 248 7799US (Houston)

       877 853 5257US Toll-free

       888 475 4499US Toll-free

 Find your local number: https://zoom.us/u/adQYOGSTh8

 Meeting ID: 941 8121 5826

 Join by SIP: 94181215826@zoomcrc.com

If you’re not able to attend the meeting, make sure to add your ideas and comments on our site in our Comments section. We’ll also be posting a meeting recap so you don’t miss out on any new details. Thank you!



Welcome to the 325 Binney St outreach site!

Thanks for visiting our new website! The purpose of this platform is to provide you with information on the 325 Binney St development and to collect all your feedback.

Please make yourself at home! Poke around to see what your neighbors are discussing and be sure to comment with your own ideas. Also hit that ‘Subscribe’ button to stay in-the-loop on all project updates. 

Everything posted here is sent straight to us at Alexandria Real Estate. We’re looking forward to hearing from you!