Construction Update 12/22/2020

Site work continues at 325 Binney Street with the sheeting installation more than half way complete. Site work and soil excavation is well underway.

Site work hours are from 7a - 6p per the Cambridge Construction Ordinance.

Christmas and New Years Day no work will be performed.

Happy New Year from the 325 Binney Street Team. Do not hesitate reaching out with any questions or concerns.