Construction Update 7/22/2021

Hello neighbors,

Site work continues at 325 Binney Street with foundation and wall installation on-going. Geothermal test well program was successful and the full installation program will begin in early August. The first tower crane is scheduled to be delivered and erected the last week in August. This will be a 3-4 day delivery and installation process.

Site work hours are from 7a - 6p per the Cambridge Construction Ordinance.

Do not hesitate reaching out with any questions or concerns.