View all updates
Update #10

Construction Update 8/16/2021

Hello neighbors,

Site work continues at 325 Binney Street with foundation and wall installation on-going. Geothermal well installation has commenced. The first tower crane is scheduled to be delivered and erected Monday August 30 through Wednesday September 1st. This will be a 3 day delivery and installation process that necessitates a portion of Fulkerson St (between Bent and Binney Street) to be closed and traffic to be detoured one block east to Sixth Streets. The street detour and closure is being coordinated by the City of Cambridge Traffic & Parking Department.

Site work hours are from 7a - 6p per the Cambridge Construction Ordinance.