Update #16

Construction Update 1/14/2022

Neighbors,

As we are nearing the finish line of the geothermal well drilling program, we wanted to provide an update on the remaining schedule.

  • Due to some challenging weather and drilling conditions recently, we will be drilling on Saturdays for the next few weeks (weather pending).
  • Saturday work will take place from 9a-6p
  • The majority of the remaining wells to be drilled are proximate to the building and further away from the residences.

We are doing everything we can to expedite the drilling progress through completion. The drilling portion of the geothermal well installation should be completed by late February or early March. As with all schedules, this is assuming favorable weather and no surprises. We will share updated schedule information as we learn it.


Thank you for your patience and understanding.