Update #19

Construction Update 5/26/2022

Neighbors,

Please note the Binney Street Extension will experience lane closures during upcoming weeks and weekends as we work to hoist the roof equipment onto the building in anticipation of the dismantling of the final Tower Crane during the weekend of June 10th - 12th.

The Binney Street Extension has reduced travel lanes for utility work in the street for a number of area projects. The lane(s) closure is anticipated to last for 8-12 weeks, but that is subject to change due to unforeseen circumstances. The lane closure is being coordinated with the City of Cambridge DPW and Eversource.

Site work hours are from 7a - 6p per the Cambridge Construction Ordinance.