Construction Update 2/26/2021

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.


The following activities will continue to take place:

  • General load out
  • Façade work
  • Interior finishes work
  • Courtyard hardscape and finishes work


Work scheduled for Saturday, 2/27 that will be contained within the job site. Typical Saturday hours of 9am-6pm apply.



Construction Update 2/18/2021

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.


The following activities will continue to take place:

  • General load out
  • Façade work
  • Interior finishes work
  • Courtyard hardscape and finishes work


Work scheduled for Saturday, 2/20 & 2/27 that will be contained within the job site. Typical Saturday hours of 9am-6pm apply.



Construction Update 2/11/2021

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.


The following activities will continue to take place:

  • General load out
  • Façade work including waterproofing, window and window surround installation, and masonry
  • Interior finishes work
  • Courtyard hardscape and finishes work


Work scheduled for Saturday, 2/13 & 2/20 that will be contained within the job site. Typical Saturday hours of 9am-6pm apply.

Please note the site will be closed on Monday 2/15 for President's Day.


Construction Update 2/5/2021

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.


The following activities will continue to take place:

  • General load out
  • Façade work including waterproofing, window and window surround installation, and masonry
  • Interior finishes work
  • Courtyard hardscape and finishes work


Work scheduled for Saturday, 2/6 & 2/13 that will be contained within the job site. Typical Saturday hours of 9am-6pm apply.


Construction Update 1/29/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

Rogers Street will be closed to all vehicular traffic. The sidewalk on the north side of Rogers Street will remain open.


The following activities will continue to take place:

  • Rogers Street roadwork
  • Installation of safety measures throughout construction site
  • Utility connection work
  • General load out
  • Façade work including waterproofing, window and window surround installation, and masonry
  • Interior finishes work
  • Courtyard hardscape and finishes work


Work scheduled for Saturday, 1/30 & 2/6 that will be contained within the job site. Typical Saturday hours of 9am-6pm apply.


Construction Update 1/22/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

Rogers Street will be closed to all vehicular traffic. The sidewalk on the north side of Rogers Street will remain open.


The following activities will continue to take place:

  • Rogers Street roadwork
  • Installation of safety measures throughout construction site
  • Utility connection work
  • General load out
  • Façade work including waterproofing, window and window surround installation, and masonry
  • Interior finishes work
  • Courtyard hardscape and finishes work


Work scheduled for Saturday, 1/23 & 1/30 that will be contained within the job site. Typical Saturday hours of 9am-6pm apply.


Construction Update 1/14/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

Rogers Street will be closed to all vehicular traffic. The sidewalk on the north side of Rogers Street will remain open.


The following activities will continue to take place:

  • Rogers Street roadwork
  • Installation of safety measures throughout construction site
  • Utility connection work
  • General load out
  • Façade work including waterproofing, window and window surround installation, and masonry
  • Interior finishes work
  • Courtyard hardscape and finishes work


Work scheduled for Saturday, 1/16 & 1/23 that will be contained within the job site. Typical Saturday hours of 9am-6pm apply.

Please note the site will be open Monday, 1/18.



Construction Update 1/8/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

Rogers Street will be closed to all vehicular traffic. The sidewalk on the north side of Rogers Street will remain open.


The following activities will continue to take place:

  • Installation of safety measures throughout construction site
  • Utility connection work
  • General load out
  • Roof installation work
  • Façade work including waterproofing, window and window surround installation, and masonry
  • Interior finishes work
  • Courtyard hardscape and finishes work


Work scheduled for Saturday, 1/9/21 & 1/16/21 that will be contained within the job site. Typical Saturday hours of 9am-6pm apply.



Construction Update 12/30/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

Rogers Street will be closed to all vehicular traffic. The sidewalk on the north side of Rogers Street will remain open.


The following activities will continue to take place:

  • Installation of safety measures throughout construction site
  • Utility connection work
  • General load out
  • Roof installation work
  • Façade work including waterproofing, window and window surround installation, and masonry
  • Interior finishes work
  • Courtyard hardscape and finishes work


Work scheduled for Saturday, 1/2/21 & 1/9/21 that will be contained within the job site. Typical Saturday hours of 9am-6pm apply.

Please note the project site closed for the New Years Day, 1/1/21; Site to be open on Thursday, 12/31/20.



Construction Update 12/23/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

Rogers Street will be closed to all vehicular traffic. The sidewalk on the north side of Rogers Street will remain open.


The following activities will continue to take place:

  • Installation of safety measures throughout construction site
  • Utility connection work
  • General load out
  • Roof installation work
  • Façade work including waterproofing, window and window surround installation, and masonry
  • Interior finishes work
  • Courtyard hardscape and finishes work


Work scheduled for Saturday, 12/26, & 1/2/21 that will be contained within the job site. Typical Saturday hours of 9am-6pm apply.

Please note the project site closed for Christmas, 12/25 and New Years, 1/1; Site to be open on Thursday, 12/24 and Thursday, 12/31.



Construction Update 12/18/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

Rogers Street will be closed to all vehicular traffic. The sidewalk on the north side of Rogers Street will remain open.


The following activities will continue to take place:

  • Installation of safety measures throughout construction site
  • Utility connection work
  • General load out
  • Roof installation work
  • Façade work including waterproofing, window and window surround installation, and masonry
  • Interior finishes work
  • Courtyard hardscape and finishes work


Work scheduled for Saturday, 12/19, 12/26, & 1/2/21 that will be contained within the job site. Typical Saturday hours of 9am-6pm apply.

Please note the project site closed for Christmas, 12/25 and New Years, 1/1; Site to be open on Thursday, 12/24 and Thursday, 12/31.



Construction Update 12/11/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

Rogers Street will be closed to all vehicular traffic. The sidewalk on the north side of Rogers Street will remain open.


The following activities will continue to take place:

  • Installation of safety measures throughout construction site
  • Utility connection work
  • General load out
  • Roof installation work
  • Façade work including waterproofing, window and window surround installation, and masonry
  • Interior finishes work
  • Courtyard hardscape and finishes work


Work scheduled for Saturday, 12/12 & 12/19 that will be contained within the job site. Typical Saturday hours of 9am-6pm apply.


Construction Update 12/4/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

Rogers Street will be closed to all vehicular traffic. The sidewalk on the north side of Rogers Street will remain open.


The following activities will continue to take place:

  • Installation of safety measures throughout construction site
  • Utility connection work
  • General load out
  • Roof installation work
  • Façade work including waterproofing, window and window surround installation, and masonry
  • Interior finishes work
  • Courtyard hardscape and finishes work


Work scheduled for Saturday, 12/5 & 12/12 that will be contained within the job site. Typical Saturday hours of 9am-6pm apply.


Construction Update 11/25/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

Rogers Street will be closed to all vehicular traffic. The sidewalk on the north side of Rogers Street will remain open.


The following activities will continue to take place:

  • Installation of safety measures throughout construction site
  • Utility connection work
  • General load out
  • Roof installation work
  • Façade work including waterproofing, window and window surround installation, and masonry
  • Interior finishes work
  • Courtyard hardscape and finishes work


The project site will be closed for the Thanksgiving holiday, 11/26 and be open Friday, 11/27.

Work scheduled for Saturday, 11/28 & 12/5 that will be contained within the job site. Typical Saturday hours of 9am-6pm apply.


Construction Update 11/20/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

Rogers Street will be closed to all vehicular traffic. The sidewalk on the north side of Rogers Street will remain open.


The following activities will continue to take place:

  • Installation of safety measures throughout construction site
  • Utility connection work
  • General load out
  • Roof installation work
  • Façade work including waterproofing, window and window surround installation, and masonry
  • Interior finishes work
  • Courtyard hardscape and finishes work


Work scheduled for Saturday, 11/21 & 11/28 that will be contained within the job site. Typical Saturday hours of 9am-6pm apply.

The project site will be closed for the Thanksgiving holiday, 11/26 and be open Friday, 11/27.



Construction Update 11/13/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

Rogers Street will be closed to all vehicular traffic. The sidewalk on the north side of Rogers Street will remain open.


The following activities will continue to take place:

  • Installation of safety measures throughout construction site
  • Utility connection work
  • General load out
  • Roof installation work
  • Façade work including waterproofing, window and window surround installation, and masonry
  • Interior finishes work
  • Courtyard hardscape and finishes work


Work scheduled for Saturday, 11/14 & 11/21 that will be contained within the job site. Typical Saturday hours of 9am-6pm apply.



Construction Update 11/5/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

Rogers Street will be closed to all vehicular traffic. The sidewalk on the north side of Rogers Street will remain open.


The following activities will continue to take place:

  • Installation of safety measures throughout construction site
  • Utility connection work
  • General load out
  • Roof installation work
  • Façade work including waterproofing, window and window surround installation, and masonry
  • Interior finishes work
  • Courtyard hardscape and finishes work


Work scheduled for Saturday, 11/7 & 11/14 that will be contained within the job site. Typical Saturday hours of 9am-6pm apply.



Construction Update 10/30/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

Rogers Street will be closed to all vehicular traffic. The sidewalk on the north side of Rogers Street will remain open.


The following activities will continue to take place:

  • Installation of safety measures throughout construction site
  • Utility connection work
  • General load out
  • Roof installation work
  • Façade work including waterproofing, window and window surround installation, and masonry
  • Interior finishes work


Work scheduled for Saturday, 10/31 & 11/7 that will be contained within the job site. Typical Saturday hours of 9am-6pm apply.



Construction Update 10/23/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

Rogers Street will be closed to all vehicular traffic. The sidewalk on the north side of Rogers Street will remain open.


The following activities will continue to take place:

  • Installation of safety measures throughout construction site
  • Utility connection work
  • General load out
  • Roof installation work
  • Façade work including waterproofing, window and window surround installation, and masonry
  • Interior work including framing and MEP rough-ins


Work scheduled for Saturday, 10/24 & 10/31 that will be contained within the job site. Typical Saturday hours of 9am-6pm apply.



Construction Update 10/16/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

Rogers Street will be closed to all vehicular traffic. The sidewalk on the north side of Rogers Street will remain open.


The following activities will continue to take place:

  • Installation of safety measures throughout construction site
  • Utility connection work
  • General load out
  • Roof installation work
  • Façade work including waterproofing, window and window surround installation, and masonry
  • Interior work including framing and MEP rough-ins


Work scheduled for Saturday, 10/17 & 10/24 that will be contained within the job site. Typical Saturday hours of 9am-6pm apply.



Construction Update 10/9/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

Rogers Street will be closed to all vehicular traffic. The sidewalk on the north side of Rogers Street will remain open.


The following activities will continue to take place:

  • Installation of safety measures throughout construction site
  • Utility connection work
  • General load out
  • Roof installation work
  • Façade work including waterproofing, window and window surround installation, and masonry
  • Interior work including framing and MEP rough-ins


Work scheduled for Saturday, 10/10 & 10/17 that will be contained within the job site. Typical Saturday hours of 9am-6pm apply.

Please note there will be minimal site activity/Interior work only on Monday, 10/12.



Construction Update 10/2/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

Rogers Street will be closed to all vehicular traffic. The sidewalk on the north side of Rogers Street will remain open.


The following activities will continue to take place:

  • Installation of safety measures throughout construction site
  • Utility connection work
  • General load out
  • Roof installation work
  • Façade work including waterproofing, window and window surround installation, and masonry
  • Interior work including framing and MEP rough-ins


Work scheduled for Saturday, 10/3 & 10/10 that will be contained within the job site. Typical Saturday hours of 9am-6pm apply.



Construction Update 9/25/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

Rogers Street will be closed to all vehicular traffic. The sidewalk on the north side of Rogers Street will remain open.


The following activities will continue to take place:

  • Installation of safety measures throughout construction site
  • Utility connection work
  • General load out
  • Roof installation work
  • Façade work including waterproofing, window and window surround installation, and masonry
  • Interior work including framing and MEP rough-ins


Work scheduled for Saturday, 9/26 & 10/3 that will be contained within the job site. Typical Saturday hours of 9am-6pm apply.



Construction Update 9/18/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

Rogers Street will be closed to all vehicular traffic. The sidewalk on the north side of Rogers Street will remain open.


The following activities will continue to take place:

  • Installation of safety measures throughout construction site
  • Utility connection work
  • General load out
  • Roof installation work
  • Façade work including waterproofing, window and window surround installation, and masonry
  • Interior work including framing and MEP rough-ins


Work scheduled for Saturday, 9/19 & 9/26 that will be contained within the job site. Typical Saturday hours of 9am-6pm apply.



Construction Update 9/10/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

Rogers Street will be closed to all vehicular traffic. The sidewalk on the north side of Rogers Street will remain open.


The following activities will continue to take place:

  • Installation of safety measures throughout construction site
  • Utility connection work
  • General load out
  • Roof installation work
  • Façade work including waterproofing, window and window surround installation, and masonry
  • Interior work including framing and MEP rough-ins


Work scheduled for Saturday, 9/12 & 9/19 that will be contained within the job site. Typical Saturday hours of 9am-6pm apply.



Construction Update 9/4/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

Rogers Street will be closed to all vehicular traffic. The sidewalk on the north side of Rogers Street will remain open.


The following activities will continue to take place:

  • Installation of safety measures throughout construction site
  • Utility connection work
  • General load out
  • Roof installation work
  • Façade work including waterproofing, window and window surround installation, and masonry
  • Interior work including framing and MEP rough-ins


Work scheduled for Saturday, 9/5 & 9/12 that will be contained within the job site. Typical Saturday hours of 9am-6pm apply.


Please note that the site will be closed for Labor Day on Monday, 9/7.



Construction Update 8/27/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

Rogers Street will be closed to all vehicular traffic. The sidewalk on the north side of Rogers Street will remain open.


The following activities will continue to take place:

  • Installation of safety measures throughout construction site
  • Utility connection work
  • General load out
  • Roof installation work
  • Façade work including waterproofing, window and window surround installation, and masonry
  • Interior work including framing and MEP rough-ins


Work scheduled for Saturday, 8/29 that will be contained within the job site. Typical Saturday hours of 9am-6pm apply.

Please note that the site will be closed for Labor Day on Monday, 9/7.



Construction Update 8/21/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

Rogers Street will be closed to all vehicular traffic. The sidewalk on the north side of Rogers Street will remain open.


The following activities will continue to take place:

  • Installation of safety measures throughout construction site
  • Utility connection work
  • General load out
  • Roof installation work
  • Façade work including waterproofing, window and window surround installation, and masonry
  • Interior work including framing and MEP rough-ins


Work scheduled for Saturday, 8/22 & 8/29 that will be contained within the job site. Typical Saturday hours of 9am-6pm apply.




Construction Update 8/14/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

Rogers Street will be closed to all vehicular traffic. The sidewalk on the north side of Rogers Street will remain open.


The following activities will continue to take place:

  • Installation of safety measures throughout construction site
  • Utility connection work
  • General load out
  • Roof installation work
  • Façade work including waterproofing, window and window surround installation, and masonry
  • Interior work including framing and MEP rough-ins


Work scheduled for Saturday, 8/15 & 8/22 that will be contained within the job site. Typical Saturday hours of 9am-6pm apply.




Construction Update 8/7/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

Rogers Street will be closed to all vehicular traffic. The sidewalk on the north side of Rogers Street will remain open.


The following activities will continue to take place:

  • Installation of safety measures throughout construction site
  • Utility connection work
  • General load out
  • Roof installation work
  • Façade work including waterproofing, window and window surround installation, and masonry
  • Interior work including framing and MEP rough-ins


Work scheduled for Saturday, 8/8 & 8/15 that will be contained within the job site. Typical Saturday hours of 9am-6pm apply.




Construction Update 7/31/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

Rogers Street will be closed to all vehicular traffic. The sidewalk on the north side of Rogers Street will remain open.


The following activities will continue to take place:

  • Installation of safety measures throughout construction site
  • Utility connection work
  • General load out
  • Roof installation work
  • Façade work including waterproofing, window and window surround installation, and masonry
  • Interior work including framing and MEP rough-ins


Work scheduled for Saturday, 8/1 & 8/8 that will be contained within the job site. Typical Saturday hours of 9am-6pm apply.




Construction Update 7/23/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

Rogers Street will be closed to all vehicular traffic. The sidewalk on the north side of Rogers Street will remain open.


The following activities will continue to take place:

  • Installation of safety measures throughout construction site
  • Utility connection work
  • General load out
  • Roof installation work
  • Façade work including waterproofing, window and window surround installation, and masonry
  • Interior work including framing and MEP rough-ins


Work scheduled for Saturday, 7/25 & 8/1 that will be contained within the job site. Typical Saturday hours of 9am-6pm apply.




Construction Update 7/17/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

Rogers Street will be closed to all vehicular traffic. The sidewalk on the north side of Rogers Street will remain open.


The following activities will continue to take place:

  • Installation of safety measures throughout construction site
  • Utility connection work
  • General load out
  • Roof installation work
  • Façade work including waterproofing, window and window surround installation, and masonry
  • Interior work including framing and MEP rough-ins


Work scheduled for Saturday, 7/18 & 7/25 that will be contained within the job site. Typical Saturday hours of 9am-6pm apply.




Construction Update 7/10/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

Rogers Street will be closed to all vehicular traffic. The sidewalk on the north side of Rogers Street will remain open.


The following activities will start and continue to take place:

  • Installation of safety and security measures throughout construction site
  • General load out of materials on Rogers St.
  • Utility connection work
  • Typical weekly deliveries (no earlier than 7am)
  • Roof installation begins
  • Facade work including waterproofing, window, window surround installation and masonry
  • Interior work including framing and MEP rough-ins





Construction Update 7/2/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

Rogers Street will be closed to all vehicular traffic. The sidewalk on the north side of Rogers Street will remain open.


The following activities will start and continue to take place:

  • Installation of safety and security measures throughout construction site
  • General load out of materials on Rogers St.
  • Utility connection work
  • Typical weekly deliveries (no earlier than 7am)
  • Roof installation begins
  • Facade work including waterproofing, window, window surround installation and masonry
  • Interior work including framing and MEP rough-ins

In compliance with the City of Cambridge COVID regulations, temperature screening will be taking place at the 2nd Street side gate on Rogers St. As a result, groups of workers may form. 


Please note the site will be open on Friday, July 3rd. Typical site hours apply.


Construction Update 6/26/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

Rogers Street will be closed to all vehicular traffic. The sidewalk on the north side of Rogers Street will remain open.


The following activities will start and continue to take place:

  • Installation of safety and security measures throughout construction site
  • General load out of materials on Rogers St.
  • Utility connection work
  • Typical weekly deliveries (no earlier than 7am)
  • Roof installation begins
  • Facade work including waterproofing, window, window surround installation and masonry
  • Interior work including framing and MEP rough-ins

In compliance with the City of Cambridge COVID regulations, temperature screening will be taking place at the 2nd Street side gate on Rogers St. As a result, groups of workers may form. 


Please note the site will be open on Friday, July 3rd. Typical site hours apply.


Construction Update 6/18/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

Rogers Street will be closed to all vehicular traffic. The sidewalk on the north side of Rogers Street will remain open.


Following the Cambridge notification posted on 5/18 to reopen construction projects by Monday, June 1st, the following activities will start and continue to take place:

  • Installation of safety and security measures throughout construction site
  • General load out of materials on Rogers St.
  • Utility connection work
  • Typical weekly deliveries (no earlier than 7am)
  • Roof installation begins
  • Facade work including waterproofing, window and window surround installation
  • Interior work including framing and MEP rough-ins

In compliance with the City of Cambridge COVID regulations, temperature screening will be taking place at the 2nd Street side gate on Rogers St. As a result, groups of workers may form. 


Below is a link to the referenced Cambridge notification:

https://www.cambridgema.gov/-/media/Files/citymanagersoffice/COVID19/amendedtemporaryemergencyconstructionorder_052020.pdf



Construction Update 6/12/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

Rogers Street will be closed to all vehicular traffic. The sidewalk on the north side of Rogers Street will remain open.


Following the Cambridge notification posted on 5/18 to reopen construction projects by Monday, June 1st, the following activities will start and continue to take place:

  • Installation of safety and security measures throughout construction site
  • General load out of materials on Rogers St.
  • Utility connection work
  • Typical weekly deliveries (no earlier than 7am)
  • Roof prep work
  • Facade work including waterproofing, window and window surround installation
  • Interior work including framing and MEP rough-ins

In compliance with the City of Cambridge COVID regulations, temperature screening will be taking place at the 2nd Street side gate on Rogers St. As a result, groups of workers may form. 


Below is a link to the referenced Cambridge notification:

https://www.cambridgema.gov/-/media/Files/citymanagersoffice/COVID19/amendedtemporaryemergencyconstructionorder_052020.pdf



Construction Update 6/5/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

Rogers Street will be closed to all vehicular traffic. The sidewalk on the north side of Rogers Street will remain open.


Following the Cambridge notification posted on 5/18 to reopen construction projects by Monday, June 1st, the following activities will start and continue to take place:

  • Installation of safety and security measures throughout construction site
  • General load out of materials on Rogers St.
  • Utility connection work
  • Typical weekly deliveries (no earlier than 7am)
  • Roof prep work
  • Facade work including waterproofing, window and window surround installation
  • Interior work including framing and MEP rough-ins

In compliance with the City of Cambridge COVID regulations, temperature screening will be taking place at the 2nd Street side gate on Rogers St. As a result, groups of workers may form. 


Below is a link to the referenced Cambridge notification:

https://www.cambridgema.gov/-/media/Files/citymanagersoffice/COVID19/amendedtemporaryemergencyconstructionorder_052020.pdf



Construction Update 5/29/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

Rogers Street will be closed to all vehicular traffic. The sidewalk on the north side of Rogers Street will remain open.


Following the Cambridge notification posted on 5/18 to reopen construction projects by Monday, June 1st, the following activities will start and continue to take place:

  • Installation of safety and security measures throughout construction site
  • General load out of materials on Rogers St.
  • Utility connection work
  • Typical weekly deliveries (no earlier than 7am)
  • Roof prep work
  • Facade work including waterproofing, window and window surround installation
  • Interior work including framing and MEP rough-ins

In compliance with the City of Cambridge COVID regulations, temperature screening will be taking place at the 2nd Street side gate on Rogers St. As a result, groups of workers may form. 


Below is a link to the referenced Cambridge notification:

https://www.cambridgema.gov/-/media/Files/citymanagersoffice/COVID19/amendedtemporaryemergencyconstructionorder_052020.pdf



Construction Update 5/22/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.


Rogers Street will be closed to all vehicular traffic. The sidewalk on the north side of Rogers Street will remain open.


Following the Cambridge notification posted on 5/18 to reopen construction projects by Monday, June 1st, the following activities will start taking place on May 26th:

  • Installation of safety and security measures throughout construction site
  • General load out of materials on Rogers St.
  • Utility connection work
  • Planning and remobilizing

 

Below is a link to the referenced Cambridge notification:

https://www.cambridgema.gov/-/media/Files/citymanagersoffice/COVID19/amendedtemporaryemergencyconstructionorder_052020.pdf



Construction Update 5/15/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.


Rogers Street will be closed to all vehicular traffic due to steel erection and panel installation. The sidewalk on the north side of Rogers Street will remain open.

 

Due to Cambridge notification posted on 3/18 to shutdown construction projects by Thursday 3/26, the following work will be occurring:

  • Installation of safety and security measures throughout construction site.
  • Temporary protection measures at the exterior including installation of windows and plastic for weather protection.
  • Temporary protection measures at roof including securing loose materials, patching holes for weather protection and roof membrane installation.
  • General load out of materials on Rogers St.
  • Utility connection work 

Construction Update 5/8/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.


Rogers Street will be closed to all vehicular traffic due to steel erection and panel installation. The sidewalk on the north side of Rogers Street will remain open.

 

Due to Cambridge notification posted on 3/18 to shutdown construction projects by Thursday 3/26, the following work will be occurring:

  • Installation of safety and security measures throughout construction site.
  • Temporary protection measures at the exterior including installation of windows and plastic for weather protection.
  • Temporary protection measures at roof including securing loose materials, patching holes for weather protection and roof membrane installation.
  • General load out of materials on Rogers St.
  • Utility connection work 

Construction Update 5/1/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.


Rogers Street will be closed to all vehicular traffic due to steel erection and panel installation. The sidewalk on the north side of Rogers Street will remain open.

 

Due to Cambridge notification posted on 3/18 to shutdown construction projects by Thursday 3/26, the following work will be occurring:

  • Installation of safety and security measures throughout construction site.
  • Temporary protection measures at the exterior including installation of windows and plastic for weather protection.
  • Temporary protection measures at roof including securing loose materials, patching holes for weather protection and roof membrane installation.
  • General load out of materials on Rogers St.
  • Utility connection work 

Construction Update 4/24/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.


Rogers Street will be closed to all vehicular traffic due to steel erection and panel installation. The sidewalk on the north side of Rogers Street will remain open.

 

Due to Cambridge notification posted on 3/18 to shutdown construction projects by Thursday 3/26, the following work will be occurring:

  • Installation of safety and security measures throughout construction site.
  • Temporary protection measures at the exterior including installation of windows and plastic for weather protection.
  • Temporary protection measures at roof including securing loose materials, patching holes for weather protection and roof membrane installation.
  • General load out of materials on Rogers St.
  • Utility connection work 

Construction Update 4/17/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.


Rogers Street will be closed to all vehicular traffic due to steel erection and panel installation. The sidewalk on the north side of Rogers Street will remain open.

 

Due to Cambridge notification posted on 3/18 to shutdown construction projects by Thursday 3/26, the following work will be occurring:

  • Installation of safety and security measures throughout construction site.
  • Temporary protection measures at the exterior including installation of windows and plastic for weather protection.
  • Temporary protection measures at roof including securing loose materials, patching holes for weather protection and roof membrane installation.
  • General load out of materials on Rogers St.
  • Utility connection work 

Construction Update 4/10/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.


Rogers Street will be closed to all vehicular traffic due to steel erection and panel installation. The sidewalk on the north side of Rogers Street will remain open.

 

Due to Cambridge notification posted on 3/18 to shutdown construction projects by Thursday 3/26, the following work will be occurring:

  • Installation of safety and security measures throughout construction site.
  • Temporary protection measures at the exterior including installation of windows and plastic for weather protection.
  • Temporary protection measures at roof including securing loose materials and patching holes for weather protection.
  • General load out of materials on Rogers St.
  • Utility connection work 

Construction Update 4/3/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.


Rogers Street will be closed to all vehicular traffic due to steel erection and panel installation. The sidewalk on the north side of Rogers Street will remain open.

 

Due to Cambridge notification posted on 3/18 to shutdown construction projects by Thursday 3/26, the following work will be occurring:

  • Installation of safety and security measures throughout construction site.
  • Temporary protection measures at the exterior including installation of windows and plastic for weather protection.
  • Temporary protection measures at roof including securing loose materials and patching holes for weather protection.
  • General load out of materials on Rogers St.
  • Utility connection work 

Construction Update 3/27/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.


Rogers Street will be closed to all vehicular traffic due to steel erection and panel installation. The sidewalk on the north side of Rogers Street will remain open.

 

Due to Cambridge notification posted on 3/18 to shutdown construction projects by Thursday 3/26, the following work will be occurring:

  • Installation of safety and security measures throughout construction site.
  • Temporary protection measures at the exterior including installation of windows and plastic for weather protection.
  • Temporary protection measures at roof including securing loose materials and patching holes for weather protection.
  • General load out of materials on Rogers St.
  • Utility connection work 

Copy of Construction Update 2/13/2020

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.


Rogers Street will be closed to all vehicular traffic due to steel erection and panel installation. The sidewalk on the north side of Rogers Street will remain open.

 

Due to Cambridge notification posted on 3/18 to shutdown construction projects by Thursday 3/26, the following work will be occurring the week of 3/23:

  • Installation of safety and security measures throughout construction site.
  • Temporary protection measures at the exterior including installation of windows and plastic for weather protection.
  • Temporary protection measures at roof including securing loose materials and patching holes for weather protection.
  • General load out of materials on Rogers St.

**Work scheduled for Saturday, 3/21 that will be contained within job site; Saturday work hours of 9am-5pm apply. No work on Saturday 3/28.**

Construction Update 2/13/2020

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Rogers Street will be closed to all vehicular traffic due to steel erection and panel installation. The sidewalk on the north side of Rogers Street will remain open.

 

The site will be active Saturday February 15th, Monday February 17th and Saturday February 22nd.

 

The site will be active after hours for two concrete pours the week of February 24th (weather dependent)

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

  • Construction vehicles will be entering and exiting the site on Rogers Street.
  • Steel, concrete, framework, and sitework subcontractors on site.
  • Interior build out beginning
  • Rogers Street is one-way westbound when not fully closed due to crane activity.
  • Dust, vibration and odor mitigation is in on-going.


Construction Update 2/7/2020

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Rogers Street will be closed to all vehicular traffic due to steel erection and panel installation. The sidewalk on the north side of Rogers Street will remain open.

 

The site will be active Saturday February 8th and Saturday February 15th.

 

The site will be active after hours for two concrete pours the week of February 24th (weather dependent).

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

  • Construction vehicles will be entering and exiting the site on Rogers Street.
  • Steel, concrete, framework, and sitework subcontractors on site.
  • Interior build out beginning
  • Rogers Street is one-way westbound when not fully closed due to crane activity.
  • Dust, vibration and odor mitigation is in on-going.

 

Construction Update 1/30/2020

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Rogers Street will be closed to all vehicular traffic due to steel erection and panel installation. The sidewalk on the north side of Rogers Street will remain open.

 

The site will be active Saturday February 1st and Saturday February 8th.

 

The site will be active after hours for a concrete pour Monday February 3rd (weather dependent).

 

The site will be active after hours for two concrete pours the week of February 24th (weather dependent)

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

  • Construction vehicles will be entering and exiting the site on Rogers Street.
  • Steel, concrete, framework, and sitework subcontractors on site.
  • Interior build out beginning
  • Rogers Street is one-way westbound when not fully closed due to crane activity.
  • Dust, vibration and odor mitigation is in on-going.


Construction Update 1/24/2020

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Rogers Street will be closed to all vehicular traffic due to steel erection and panel installation. The sidewalk on the north side of Rogers Street will remain open.

 

The site will be active Saturday January 25th and Saturday February 1st.   

 

The site will be active after hours for two concrete pours the week of January 27th, likely Tuesday 1/28 and Friday 1/31 (weather dependent).

 

The site will be active after hours for two concrete pours the week of February 24th.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

  • Construction vehicles will be entering and exiting the site on Rogers Street.
  • Steel, concrete, framework, and sitework subcontractors on site.
  • Interior build out beginning
  • Rogers Street is one-way westbound when not fully closed due to crane activity.
  • Dust, vibration and odor mitigation is in on-going.


Construction Update 1/16/2020

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Rogers Street will be closed to all vehicular traffic due to steel erection and panel installation. The sidewalk on the north side of Rogers Street will remain open.

 

The site will be active Saturday January 18th and Saturday January 25th

 

The site will be active after hours for two concrete pours the week of January 27th.

 

The site will be active after hours for two concrete pours the week of February 24th.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

  • Construction vehicles will be entering and exiting the site on Rogers Street.
  • Steel, concrete, framework, and sitework subcontractors on site.
  • Interior build out beginning
  • Rogers Street is one-way westbound when not fully closed due to crane activity.
  • Dust, vibration and odor mitigation is in on-going.


Construction Update 1/10/2020

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Rogers Street will be closed to all vehicular traffic due to steel erection and panel installation. The sidewalk on the north side of Rogers Street will remain open.

 

The site will be active Saturday January 11th and Saturday January 18th

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

  • Construction vehicles will be entering and exiting the site on Rogers Street.
  • Steel, concrete, framework, and sitework subcontractors on site.
  • Interior build out beginning
  • Rogers Street is one-way westbound when not fully closed due to crane activity.
  • Dust, vibration and odor mitigation is in on-going.


Construction Update 1/2/2020

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.


Rogers Street will be closed to all vehicular traffic due to steel erection and panel installation. The sidewalk on the north side of Rogers Street will remain open.

 

The site will be active Saturday 1/4 & 1/11.

 

The site will be active for longer than usual on Thursday 1/2 & Monday 1/6 for concrete placement.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

  • Construction vehicles will be entering and exiting the site on Rogers Street.
  • Steel, concrete, framework, and sitework subcontractors on site.
  • Interior build out beginning
  • Rogers Street is one-way westbound when not fully closed due to crane activity.
  • Dust, vibration and odor mitigation is in on-going.


Construction Update 12/26

Neighbors,


Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.


Rogers Street will be closed to all vehicular traffic due to steel erection and panel installation. The sidewalk on the north side of Rogers Street will remain open.

 

The site will be active Saturday December 28th.

 

The site will be active for longer than usual on Monday 12/30 for concrete placement.

 

The site will be closed on 12/25 and 1/1.  

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

  • Construction vehicles will be entering and exiting the site on Rogers Street.
  • Steel, concrete, framework, and sitework subcontractors on site.
  • Interior build out beginning
  • Rogers Street is one-way westbound when not fully closed due to crane activity.
  • Dust, vibration and odor mitigation is in on-going.


Construction Update 12/19/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Rogers Street will be closed to all vehicular traffic due to steel erection and panel installation. The sidewalk on the north side of Rogers Street will remain open.

 

The site will be active Saturday December 21st and Saturday December 28th.

 

The site will be active for longer than usual on Monday 12/30 for concrete placement.

 

The site will be closed on 12/25 and 1/1.   

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

  • Construction vehicles will be entering and exiting the site on Rogers Street.
  • Steel, concrete, framework, and sitework subcontractors on site.
  • Interior build out beginning
  • Rogers Street is one-way westbound when not fully closed due to crane activity.
  • Dust, vibration and odor mitigation is in on-going.


Construction Update 12/12/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Rogers Street will be closed to all vehicular traffic due to steel erection and panel installation. The sidewalk on the north side of Rogers Street will remain open.

 

The site will be active Saturday December 14th and Saturday December 21st

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

  • Construction vehicles will be entering and exiting the site on Rogers Street.
  • Steel, concrete, framework, and sitework subcontractors on site.
  • Interior build out beginning
  • Rogers Street is one-way westbound when not fully closed due to crane activity.
  • Dust, vibration and odor mitigation is in on-going.

 

Construction Update 12/6/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Rogers Street will be closed to all vehicular traffic due to steel erection and panel installation. The sidewalk on the north side of Rogers Street will remain open.

 

The site will be active Saturday December 7th and Saturday December 14th

 

The site will be active for longer than normal hours Monday 12/9 utility connection work.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

  • Construction vehicles will be entering and exiting the site on Rogers Street.
  • Steel, concrete, framework, and sitework subcontractors on site.
  • Interior build out beginning
  • Rogers Street is one-way westbound when not fully closed due to crane activity.
  • Dust, vibration and odor mitigation is in on-going.


Construction Update 11/27/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Rogers Street will be closed to all vehicular traffic due to steel erection and panel installation. The sidewalk on the north side of Rogers Street will remain open.

 

The site will be active Saturday December 7th

 

The site will be active for longer than normal hours Tuesday 12/3 for a concrete pour.

 

The site will be closed for Thanksgiving Thursday 11/28.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

  • Construction vehicles will be entering and exiting the site on Rogers Street.
  • Steel, concrete, framework, and sitework subcontractors on site.
  • Interior build out beginning
  • Rogers Street is one-way westbound when not fully closed due to crane activity.
  • Dust, vibration and odor mitigation is in on-going.


Construction Update 11/21/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Rogers Street will be closed to all vehicular traffic due to steel erection and panel installation. The sidewalk on the north side of Rogers Street will remain open.

 

The site will be active Saturday November 23rd

 

The site will be active for longer than normal hours Monday 11/25 for a concrete pour.

 

The site will be closed for Thanksgiving Thursday 11/28.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

  • Construction vehicles will be entering and exiting the site on Rogers Street.
  • Steel, concrete, framework, and sitework subcontractors on site.
  • Interior build out beginning
  • Rogers Street is one-way westbound when not fully closed due to crane activity.
  • Dust, vibration and odor mitigation is in on-going.


Construction Update 11/14/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Rogers Street will be closed to all vehicular traffic due to steel erection and panel installation. The sidewalk on the north side of Rogers Street will remain open.

 

The site will be active Saturday November 16th and Saturday November 23rd

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

  • Construction vehicles will be entering and exiting the site on Rogers Street.
  • Steel, concrete, framework, and sitework subcontractors on site.
  • Interior build out beginning
  • Rogers Street is one-way westbound when not fully closed due to crane activity.
  • Dust, vibration and odor mitigation is in on-going.


Construction Update 11/7/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Rogers Street will be closed to all vehicular traffic due to steel erection and panel installation. The sidewalk on the north side of Rogers Street will remain open.

 

The site will be active Saturday November 9th and Saturday November 16th

 

The site will be closed on Monday November 11th for Veteran’s Day.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

  • Construction vehicles will be entering and exiting the site on Rogers Street.
  • Steel, concrete, framework, and sitework subcontractors on site.
  • Interior build out beginning
  • Rogers Street is one-way westbound when not fully closed due to crane activity.
  • Dust, vibration and odor mitigation is in on-going.


Construction Update 10/31/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Rogers Street will be closed to all vehicular traffic due to steel erection and panel installation. The sidewalk on the north side of Rogers Street will remain open.

 

The site will be active Saturday November 2nd and Saturday November 9th

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

  • Construction vehicles will be entering and exiting the site on Rogers Street.
  • Steel, concrete, framework, and sitework subcontractors on site.
  • Interior build out beginning
  • Rogers Street is one-way westbound when not fully closed due to crane activity.
  • Dust, vibration and odor mitigation is in on-going.


Construction Update 10/24/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Rogers Street will be closed to all vehicular traffic due to steel erection and panel installation. The sidewalk on the north side of Rogers Street will remain open.

 

The site will be active Saturday October 26th and Saturday November 2nd.  

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

  • Construction vehicles will be entering and exiting the site on Rogers Street.
  • Steel and sitework subcontractors on site.
  • Rogers Street is one-way westbound when not fully closed due to crane activity.
  • Dust, vibration and odor mitigation is in on-going.


Construction Update 10/18/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Rogers Street will be closed to all vehicular traffic due to steel erection and panel installation. The sidewalk on the north side of Rogers Street will remain open.

 

The site will be active Saturday October 19th and Saturday October 26th.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

  • Construction vehicles will be entering and exiting the site on Rogers Street.
  • Steel and sitework subcontractors on site.
  • Rogers Street is one-way westbound when not fully closed due to crane activity.
  • Dust, vibration and odor mitigation is in on-going.


Construction Update 10/10/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Rogers Street will be closed to all vehicular traffic due to steel erection and panel installation. The sidewalk on the north side of Rogers Street will remain open.

 

The site will be active Saturday October 12th and Saturday October 19th.

 

The site will be closed for the holiday on Monday October 14th.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

  • Construction vehicles will be entering and exiting the site on Rogers Street.
  • Steel and sitework subcontractors on site.
  • Rogers Street is one-way westbound when not fully closed due to crane activity.
  • Dust, vibration and odor mitigation is in on-going.


Construction Update 10/3/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Rogers Street will be closed to all vehicular traffic due to steel erection. The sidewalk on the north side of Rogers Street will remain open.

 

The site will be active Saturday October 5th and Saturday October 12th.    

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

  • Construction vehicles will be entering and exiting the site on Rogers Street.
  • Steel and sitework subcontractors on site.
  • Rogers Street is one-way westbound when not fully closed due to crane activity.
  • Dust, vibration and odor mitigation is in on-going.


Construction Update 9/27/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Rogers Street will be closed to all vehicular traffic due to steel erection. The sidewalk on the north side of Rogers Street will remain open.

 

The site will be active Saturday September 28th and Saturday October 5th.   

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

  • Construction vehicles will be entering and exiting the site on Rogers Street.
  • Steel and sitework subcontractors on site.
  • Rogers Street is one-way westbound when not fully closed due to crane activity.
  • Dust, vibration and odor mitigation is in on-going.


Construction Update 9/19/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Beginning the week of July 29, 2019 Rogers Street will be closed to all vehicular traffic for approximately 8 weeks due to steel erection. The sidewalk on the north side of Rogers Street will remain open.

 

The site will be active Saturday September 21st and Saturday September 28th

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

  • Construction vehicles will be entering and exiting the site on Rogers Street.
  • Steel and sitework subcontractors on site.
  • Rogers Street is one-way westbound when not fully closed due to crane activity.
  • Dust, vibration and odor mitigation is in on-going.


Construction Update 9/13/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Beginning the week of July 29, 2019 Rogers Street will be closed to all vehicular traffic for approximately 8 weeks due to steel erection. The sidewalk on the north side of Rogers Street will remain open.

 

The site will be active Saturday September 14th and Saturday September 21st

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

  • Construction vehicles will be entering and exiting the site on Rogers Street.
  • Steel and sitework subcontractors on site.
  • Rogers Street is one-way westbound when not fully closed due to crane activity.
  • Dust, vibration and odor mitigation is in on-going.

 

Check out the 50 Rogers Street project website (see link / url to copy below). Sign up to receive updates, post comments and questions, see the latest renderings.Neighbors,

 


Construction Update 9/5/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Beginning the week of July 29, 2019 Rogers Street will be closed to all vehicular traffic for approximately 8 weeks due to steel erection. The sidewalk on the north side of Rogers Street will remain open.

 

The site will be active Saturday September 7th and Saturday September 14th.  

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

·        Construction vehicles will be entering and exiting the site on Rogers Street.

·        Steel and sitework subcontractors on site.

·        Rogers Street is one-way westbound when not fully closed due to crane activity.

·        Dust, vibration and odor mitigation is in on-going.

Construction Update 8/29/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Beginning the week of July 29, 2019 Rogers Street will be closed to all vehicular traffic for approximately 8 weeks due to steel erection. The sidewalk on the north side of Rogers Street will remain open.

 

The site will be active Saturday September 7th.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

·      Construction vehicles will be entering and exiting the site on Rogers Street.

·      Steel and sitework subcontractors on site.

·      Rogers Street is one-way westbound when not fully closed due to crane activity.

·      Dust, vibration and odor mitigation is in on-going.

Construction Update 8/15/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Beginning the week of July 29, 2019 Rogers Street will be closed to all vehicular traffic for approximately 8 weeks due to steel erection. The sidewalk on the north side of Rogers Street will remain open.

 

The site will be active Saturday August 17th and Saturday August 24th.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

·      Construction vehicles will be entering and exiting the site on Rogers Street.

·      Steel and sitework subcontractors on site.

·      Rogers Street is one-way westbound when not fully closed due to crane activity.

·      Dust, vibration and odor mitigation is in on-going.

 


Construction Update 8/7/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Beginning the week of July 29, 2019 Rogers Street will be closed to all vehicular traffic for approximately 8 weeks due to steel erection. The sidewalk on the north side of Rogers Street will remain open.

 

The site will be active Saturday August 17th and Saturday August 24th.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

·      Construction vehicles will be entering and exiting the site on Rogers Street.

·      Steel and sitework subcontractors on site.

·      Rogers Street is one-way westbound when not fully closed due to crane activity.

·      Dust, vibration and odor mitigation is in on-going.

Construction Update 8/1/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Beginning the week of July 29, 2019 Rogers Street will be closed to all vehicular traffic for approximately 8 weeks due to steel erection. The sidewalk on the north side of Rogers Street will remain open.

 

The site will be active Saturday August 10th and Saturday August 17th.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

·      Construction vehicles will be entering and exiting the site on Rogers Street.

·      Steel and sitework subcontractors on site.

·      Rogers Street is one-way westbound when not fully closed due to crane activity.

·      Dust, vibration and odor mitigation is in on-going.

 

Check out the 50 Rogers Street project website (see link / url to copy below). Sign up to receive updates, post comments and questions, see the latest renderings.

 

https://courbanize.com/projects/50rogers/information


Thanks,

Michelle

Construction Update 7/25/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Beginning the week of July 29, 2019 Rogers Street will be closed to all vehicular traffic for approximately 8 weeks due to steel erection. The sidewalk on the north side of Rogers Street will remain open.

 

The westbound lane of Binney Street will remain closed for the week of July 29th . This closure is anticipated to last for the entire week.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

·      Construction vehicles will be entering and exiting the site on Rogers Street.

·      Steel and sitework subcontractors on site.

·      Rogers Street is one-way westbound when not fully closed due to crane activity.

·      Dust, vibration and odor mitigation is in on-going.

Construction Update 7/19/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Beginning the week of July 22, 2019 Rogers Street will be closed to all vehicular traffic for approximately 8 weeks due to steel erection. The sidewalk on the north side of Rogers Street will remain open.

 

The westbound lane of Binney Street will remain closed for the week of July 22nd . This closure is anticipated to last for the entire week.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

·      Construction vehicles will be entering and exiting the site on Rogers Street.

·      Steel and sitework subcontractors on site.

·      Rogers Street is one-way westbound when not fully closed due to crane activity.

·      Dust, vibration and odor mitigation is in on-going.

 


Construction Update 7/12/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Beginning July 22, 2019 Rogers Street will be closed to all vehicular traffic for approximately 8 weeks due to steel erection. The sidewalk on the north side of Rogers Street will remain open.

 

Beginning July 15th we are coordinating with Cambridge DPW for the westbound lane closure of Binney Street. This closure is anticipated to last for two weeks.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

·      Construction vehicles will be entering and exiting the site on Rogers Street.

·      Steel and sitework  subcontractors on site.

·      Rogers Street is one-way westbound when not fully closed due to crane activity.

·      Dust, vibration and odor mitigation is in on-going.

Construction Update 7/3/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Beginning July 22, 2019 Rogers Street will be closed to all vehicular traffic for approximately 8 weeks due to steel erection. The sidewalk on the north side of Rogers Street will remain open.

 

Beginning July 15th we are coordinating with Cambridge DPW for the westbound lane closure of Binney Street. This closure is anticipated to last for two weeks.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

·      Construction vehicles will be entering and exiting the site on Rogers Street.

·      Steel, sitework, concrete subcontractors on site.

·      Rogers Street is one-way westbound when not fully closed due to crane activity.

·      Dust, vibration and odor mitigation is in on-going.

Construction Update 6/27/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Beginning July 22, 2019 Rogers Street will be closed to all vehicular traffic for approximately 8 weeks due to steel erection. The sidewalk on the north side of Rogers Street will remain open.

 

The week of July 1st we are coordinating with Cambridge DPW for the westbound lane closure of Binney Street. This partial closure is anticipated to last for one week.

 

The week of July 15th we are coordinating with Cambridge DPW for the westbound lane closure of Binney Street. This partial closure is anticipated to last for one week.

 

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

·      Construction vehicles will be entering and exiting the site on Rogers Street.

·      Steel, sitework, concrete subcontractors on site.

·      Rogers Street is one-way westbound when not fully closed due to crane activity.

·      Dust, vibration and odor mitigation is in on-going.

Construction Update 6/19/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Beginning July 1, 2019 Rogers Street will be closed to all vehicular traffic for approximately 8 weeks due to steel erection. The sidewalk on the north side of Rogers Street will remain open.

 

The week of July 8th we are coordinating with Cambridge DPW for the partial closure of Binney Street. This partial closure is anticipated to last for one week.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

·      Construction vehicles will be entering and exiting the site on Rogers Street.

·      Steel subcontractor fully mobilized on site.

·      Rogers Street is one-way westbound when no fully closed due to crane activity.

·      Dust, vibration and odor mitigation is in on-going.

Construction Update 6/12/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Rogers Street will be open one-way in the westward direction on Tuesday June 18th.  

 

Beginning July 1, 2019 Rogers Street will be closed to all vehicular traffic for approximately 8 weeks due to steel erection. The sidewalk on the north side of Rogers Street will remain open.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

·      Construction vehicles will be entering and exiting the site on Rogers Street.

·      Steel subcontractor fully mobilized on site.

·      Rogers Street is one-way westbound when no fully closed due to crane activity.


·      Dust, vibration and odor mitigation is in on-going.Neighbors,

 


Construction Update 6/6/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

The site will be open Saturday June 8, 2019 from 9a – 5p.

 

Rogers Street will be closed for 3-4 weeks to allow for steel delivery and installation. The sidewalk on the north side of Rogers Street will remain open.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

·      Construction vehicles will be entering and exiting the site on Rogers Street.

·      Steel subcontractor fully mobilized on site.

·      Rogers Street is one-way westbound when no fully closed due to crane activity.

·      Dewatering process is on-going and will continue for approximately six months.

·      Dust, vibration and odor mitigation is in on-going.

Construction Update 5/31/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

The site will be open Saturday June 1, 2019 from 9a – 5p.

 

Rogers Street will be closed for 3-4 weeks to allow for steel delivery and installation. The sidewalk on the north side of Rogers Street will remain open.

 

Note that there may be intermittent lane closures on Binney Street to support concrete operations.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

·      Construction vehicles will be entering and exiting the site on Rogers Street.

·      Steel subcontractor fully mobilized on site.

·      Rogers Street is one-way westbound when no fully closed due to crane activity.

·      Dewatering process is on-going and will continue for approximately six months.

·      Dust, vibration and odor mitigation is in on-going.

Weekly Construction Update 5/23/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

The site is scheduled to be open Saturday June 1, 2019.

 

Rogers Street will be closed for 3-4 weeks to allow for steel delivery and installation. The sidewalk on the north side of Rogers Street will remain open.

 

Note that there may be intermittent lane closures on Binney Street to support concrete operations.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

·      Construction vehicles will be entering and exiting the site on Rogers Street.

·      Steel subcontractor fully mobilized on site.

·      Rogers Street is one-way westbound when no fully closed due to crane activity.

·      Dewatering process is on-going and will continue for approximately six months.

·      Dust, vibration and odor mitigation is in on-going.Neighbors,

 

Construction Update 5/18/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Rogers Street will be closed for 3-4 weeks to allow for steel delivery and installation. The sidewalk on the north side of Rogers Street will remain open.

 

Note that there may be intermittent lane closures on Binney Street to support concrete operations.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

·      Construction vehicles will be entering and exiting the site on Rogers Street.

·      Steel subcontractor fully mobilized on site.

·      Rogers Street is one-way westbound when no fully closed due to crane activity.

·      Dewatering process is on-going and will continue for approximately six months.

·      Dust, vibration and odor mitigation is in on-going.

Weekly Construction Update 5/8/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Rogers Street will be closed for 3-4 weeks to allow for steel delivery and installation. The sidewalk on the north side of Rogers Street will remain open.

 

Note that there may be intermittent lane closures on Binney Street to support concrete operations.

 

The site will be open from 9a-6p on Saturday May 11th

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

·      Construction vehicles will be entering and exiting the site on Rogers Street.

·      Concrete subcontractor continuing work on-site.

·      Rogers Street is one-way westbound.

·      Dewatering process is on-going and will continue for approximately six months.

·      Dust, vibration and odor mitigation is in on-going.

Construction Update 5/3/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

As of May 6th Rogers Street will be closed for 3-4 weeks to allow for steel delivery and installation. The sidewalk on the north side of Rogers Street will remain open.

 

Note that there may be intermittent lane closures on Binney Street to support concrete operations.

 

The site will be open on Saturday May 4th.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

·      Construction vehicles will be entering and exiting the site on Rogers Street.

·      Concrete subcontractor continuing work on-site.

·      Rogers Street is one-way westbound.

·      Dewatering process is on-going and will continue for approximately six months.

·      Dust, vibration and odor mitigation is in on-going.

Construction Update 4/26/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

As of May 6th Rogers Street will be closed for 3-4 weeks to allow for steel delivery and installation. The sidewalk on the north side of Rogers Street will remain open.

Note that there may be intermittent lane closures on Binney Street to support concrete operations.

The site will be open on Saturday May 4th.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

·        Construction vehicles will be entering and exiting the site on Rogers Street.

·        Concrete subcontractor continuing work on-site.

·        Rogers Street is one-way westbound.

·        Dewatering process is on-going and will continue for approximately six months.

·        Dust, vibration and odor mitigation is in on-going.

Construction Update 4/12/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Note that there may be intermittent lane closures on Binney Street to support concrete operations.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

·      Construction vehicles will be entering and exiting the site on Rogers Street.

·      Concrete subcontractor continuing work on-site.

·      Rogers Street is one-way westbound.

·      Dewatering process is on-going and will continue for approximately six months.

·      Dust, vibration and odor mitigation is in on-going.

Construction Update 4/4/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Note that there may be intermittent lane closures on Binney Street to support concrete operations.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

·      Construction vehicles will be entering and exiting the site on Rogers Street.

·      Concrete subcontractor continuing work on-site.

·      Rogers Street is one-way westbound.

·      Dewatering process is on-going and will continue for approximately six months.

·      Dust, vibration and odor mitigation is in on-going.

Construction Update 3/28/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Note that there may be intermittent lane closures on Binney Street to support concrete operations.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

·      Construction vehicles will be entering and exiting the site on Rogers Street.

·      Concrete subcontractor continuing work on-site.

·      Rogers Street is one-way westbound.

·      Dewatering process is on-going and will continue for approximately six months.

·      Dust, vibration and odor mitigation is in on-going.

Weekly Construction Update 3/21/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Note that there may be intermittent lane closures on Binney Street to support concrete operations.

 

The site will be open Saturday March 23rd and Saturday March 30th. Working hours will be 9a – 5p.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

·      Construction vehicles will be entering and exiting the site on Rogers Street.

·      Concrete subcontractor continuing work on-site.

·      Rogers Street is one-way westbound.

·      Dewatering process is on-going and will continue for approximately six months.

·      Dust, vibration and odor mitigation is in on-going.

Construction Update 3/14/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Note that there may be intermittent lane closures on Binney Street to support concrete operations.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

·      Construction vehicles will be entering and exiting the site on Rogers Street.

·      Rogers Street is one-way westbound.

·      Dewatering process is on-going and will continue for approximately six months.

·      Dust, vibration and odor mitigation is in on-going.

 


Weekly Construction Update 3/8/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Note that there may be intermittent lane closures on Binney Street to support concrete operations.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

·      Construction vehicles will be entering and exiting the site on Rogers Street.

·      Rogers Street is one-way westbound.

·      Dewatering process is on-going and will continue for approximately six months.

·      Dust, vibration and odor mitigation is in on-going.

Construction Update 2/28/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Note that there may be intermittent lane closures on Binney Street to support concrete operations.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

·      Construction vehicles will be entering and exiting the site on Rogers Street.

·      Rogers Street is one-way westbound.

·      Dewatering process is on-going and will continue for approximately six months.

·      Dust, vibration and odor mitigation is in on-going.

Weekly Construction Update 2/14/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

The site will be closed on Monday February 18, 2019.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

·      Construction vehicles will be entering and exiting the site on Rogers Street.

·      Rogers Street is one-way westbound.

·      Dewatering process is on-going and will continue for approximately six months.

·      Dust, vibration and odor mitigation is in on-going.

Construction Update 2/8/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

·      Construction vehicles will be entering and exiting the site on Rogers Street.

·      Rogers Street is one-way westbound.

·      Dewatering process is on-going and will continue for approximately six months.

·      Dust, vibration and odor mitigation is in on-going.

Construction Update 1/31/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

·      Excavation on the site is on-going.

·      Construction vehicles will be entering and exiting the site on Rogers Street.

·      Rogers Street is one-way westbound.

·      Dewatering process is on-going and will continue for approximately six months.

·      Dust, vibration and odor mitigation is in on-going.

 

Construction Update 1/25/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

·      Excavation on the site is on-going.

·      Construction vehicles will be entering and exiting the site on Rogers Street.

·      Rogers Street is one-way westbound.

·      Dewatering is on-going and will continue for approximately six months.

·      Dust, vibration and odor mitigation is in on-going.

Weekly Construction Update 12/18/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

The site will be open Saturday January 19th.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

·      Excavation on the site is on-going.

·      Construction vehicles will be entering and exiting the site on Rogers Street.

·      Site fence will be moved out to encompass the south driving lane on Rogers. Rogers Street becomes westbound one-way.

·      Soil removal continues.

·      Dewatering process will begin and will continue for approximately six months.

·      Dust, vibration and odor mitigation is in on-going.


Construction Update 1/11/19

Neighbors,

 

Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

The site will be open Saturday January 12th.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

·      Excavation on the site is on-going.

·      Construction vehicles will be entering and exiting the site on Rogers Street.

·      Site fence will be moved out to encompass the south driving lane on Rogers. Rogers Street becomes westbound one-way.

·      Soil removal continues.

·      Dewatering process will begin and will continue for approximately six months.

·      Dust, vibration and odor mitigation is in on-going.

Construction Update 1/4/19

Neighbors,

 

Happy New Year! Please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

The site will be open Saturday January 5th.

The site will be open Saturday January 12th.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

·      Excavation on the site is on-going and will continue for the remainder of the year.

·      Construction vehicles will be entering and exiting the site on Rogers Street.

·      Site fence will be moved out to encompass the south driving lane on Rogers. Rogers Street becomes westbound one-way.

·      Soil removal continues.

·      Dewatering process will begin and will continue for approximately six months.

·      Dust, vibration and odor mitigation is in on-going.

Construction Update 10/21/18

Neighbors,

 

Happy Holidays, please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

The site will be close early on Monday December 24, 2018.

The site will be closed on Tuesday December 25, 2018.

The site will be open on Saturday December 29, 2018 with work beginning at 9a.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

·      Excavation on the site is on-going and will continue for the remainder of the year.

·      Construction vehicles will be entering and exiting the site on Rogers Street.

·      Site fence will be moved out to encompass the south driving lane on Rogers. Rogers Street becomes westbound one-way.

·      Soil removal continues.

·      Dewatering process will begin and will continue for approximately six months.

·      Dust, vibration and odor mitigation is in on-going.

Construction Update 12/13/18

Neighbors,

Below, please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

The site will be open on Saturday December 15, 2018 with work beginning at 9a.

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

·      Excavation on the site is on-going and will continue for the remainder of the year.

·      Construction vehicles will be entering and exiting the site on Rogers Street.

·      Site fence will be moved out to encompass the south driving lane on Rogers. Rogers Street becomes westbound one-way.

·      Soil removal continues.

·      Dewatering process will begin and will continue for approximately six months.

·      Dust, vibration and odor mitigation is in on-going.

 

Weekly Construction Update 12/6/18

Neighbors,

 

Below, please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail has been requested to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

·      Excavation on the site is on-going and will continue for the remainder of the year.

·      The remaining foundation sheets will be installed.

·      Construction vehicles will be entering and exiting the site on Rogers Street.

·      Site fence will be moved out to encompass the south driving lane on Rogers. Rogers Street becomes westbound one-way.

·      Soil removal continues.

·      Dewatering process will begin and will continue for approximately six months.

·      Dust, vibration and odor mitigation is in on-going.

·      Installation of final foundation sheets will take place.



Thanks,

Michelle

Construction Update 11/30/18

Neighbors,

Below, please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-5p. A police detail is scheduled to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

·      Excavation on the site is on-going and will continue for the remainder of the year.

·      The remaining foundation sheets will be installed.

·      Construction vehicles will be entering and exiting the site on Rogers Street.

·      Site fence will be moved out to encompass the south driving lane on Rogers. Rogers Street becomes eastbound one-way.

·      Soil removal continues.

·      Dewatering process will begin and will continue for approximately six months.

·      Dust, vibration and odor mitigation is in on-going.

Construction Update 11/21/18

Neighbors,


Below, please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-4p. A police detail is scheduled to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Note that the City of Cambridge is conducting sewer repair work in Rogers Street which may necessitate closing all or a portion of Rogers Street for the next few weeks. Please contact Cambridge DPW with further questions about the work within Rogers Street.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

·      Excavation on the site is on-going and will continue for the remainder of the year.

·      The remaining foundation sheets will be installed

·      Construction vehicles will be entering and exiting the site on Rogers Street.

·      Site fence will be moved out to encompass the south driving lane on Rogers. Rogers Street becomes westbound one-way

·      Soil removal continues.

·      Dust, vibration and odor mitigation is in on-going.

Construction Update 11/16/18


Neighbors,

Below, please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-4p. A police detail is scheduled to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

Note that the City of Cambridge is conducting sewer repair work in Rogers Street which may necessitate closing all or a portion of Rogers Street for the next few weeks. Please contact Cambridge DPW with further questions about the work within Rogers Street.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

·      Excavation on the site is on-going and will continue for the remainder of the year.

·      Construction vehicles will be entering and exiting the site on Rogers Street.

·      Soil removal continues.

·      Dust, vibration and odor mitigation is in on-going.

Construction Update 11/9/18

Neighbors,

Below, please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-4p. A police detail is scheduled to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

Note that the City of Cambridge is conducting sewer repair work in Rogers Street which may necessitate closing all or a portion of Rogers Street for the next few weeks. Please contact Cambridge DPW with further questions about the work within Rogers Street.

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

·      Excavation on the site is on-going and will continue for the remainder of the year.

·      Construction vehicles will be entering and exiting the site on Rogers Street.

·      Soil removal continues.

·      Dust, vibration and odor mitigation is in on-going.

Construction Update 11/1/18

Neighbors,

 

Below, please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-4p. A police detail is scheduled to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Note that the City of Cambridge is conducting sewer repair work in Rogers Street which may necessitate closing all or a portion of Rogers Street for the next few weeks. Please contact Cambridge DPW with further questions about the work within Rogers Street.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise and truck traffic.

·      Excavation on the site is on-going and will continue for the remainder of the year.

·      Installation of foundation sheet piles will continue.

·      Construction vehicles will be entering and exiting the site on Rogers Street.

·      Soil removal from the site has begun.

·      Dust, vibration and odor mitigation is in on-going.

Construction Update 10/25/18

Neighbors,

Below, please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-4p. A police detail is scheduled to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

 

Note that the City of Cambridge is conducting sewer repair work in Rogers Street which may necessitate closing all or a portion of Rogers Street for the next few weeks. Please contact Cambridge DPW with further questions about the work within Rogers Street.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise.

·      Excavation on the site is on-going and will continue for the remainder of the year.

·      Installation of foundation sheet piles has begun.

·      Construction vehicles will be entering and exiting the site on Rogers Street (See attached logistics plan).

·      Demolition is on-going.

·      Dust, vibration and odor mitigation is in on-going.

Construction Update 10/18/18

Neighbors,

Below, please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-4p. A police detail is scheduled to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

Note that the City of Cambridge is conducting sewer repair work in Rogers Street which may necessitate closing all or a portion of Rogers Street for the next few weeks. Please contact Cambridge DPW with further questions about the work within Rogers Street.

The following activity involves the use of heavy construction and trucking equipment and will create noise.

·      Excavation on the site is on-going and will continue for the remainder of the year.

·      Foundation sheet installation will begin.

·      Utility infrastructure investigation on Binney Street will begin on Saturday October 6th.

·      Construction vehicles will be entering and exiting the site on Rogers Street

·      Demolition is on-going.

·      Dust, vibration and odor mitigation is in on-going.

Construction Update 10/11/18

Neighbors,

Below, please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-4p. A police detail is scheduled to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

Note that the City of Cambridge is conducting sewer repair work in Rogers Street which may necessitate closing all or a portion of Rogers Street for the next few weeks. Please contact Cambridge DPW with further questions about the work within Rogers Street.

The following activity involves the use of heavy construction and trucking equipment and will create noise.

·      Excavation on the site is on-going and will continue for the remainder of the year.

·      Site fence will be moved north to include a travel lane on Rogers Street; making Rogers Street one way westward.

·      Preparation for foundation sheet installation will begin.

·      Sheet pile installation will begin.

·      Construction vehicles will be entering and exiting the site on Rogers Street

·      Demolition is on-going.

·      Dust, vibration and odor mitigation is in on-going.

Construction Update 10/4/18

Neighbors,

Below, please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-4p. A police detail is scheduled to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

Note that the City of Cambridge is conducting sewer repair work in Rogers Street which may necessitate closing all or a portion of Rogers Street for the next few weeks. Please contact Cambridge DPW with further questions about the work within Rogers Street.

The following activity involves the use of heavy construction and trucking equipment and will create noise.

·      Excavation on the site is on-going and will continue for the remainder of the year.

·      Site fence will be moved north to include a travel lane on Rogers Street; making Rogers Street one way westward.

·      Preparation for foundation sheet installation will begin.

·      Utility infrastructure investigation on Binney Street will begin on Saturday October 6th.

·      Construction vehicles will be entering and exiting the site on Rogers Street (See attached logistics plan).

·      Demolition is on-going.

·      Dust, vibration and odor mitigation is in on-going.

Construction Update 9/28/18

Neighbors,

Below, please find this week’s 50 Rogers Street weekly construction update. Typical site working hours are Monday – Friday 7a-4p. A police detail is scheduled to be on site to assist with pedestrian safety. Please do not hesitate reaching out to a team member with any questions.

Note that the City of Cambridge is conducting sewer repair work in Rogers Street which may necessitate closing all or a portion of Rogers Street for the next few weeks. Please contact Cambridge DPW with further questions about the work within Rogers Street.

 

The following activity involves the use of heavy construction and trucking equipment and will create noise.

·      Excavation on the site is on-going and will continue for the remainder of the year.

·      Site fence will be moved north to include a travel lane on Rogers Street; making Rogers Street one way westward.

·      Preparation for foundation sheet installation will begin.

·      Utility infrastructure investigation on Binney Street will begin on Saturday October 6th.

·      Construction vehicles will be entering and exiting the site on Rogers Street (See attached logistics plan).

·      Demolition is on-going.

·      Dust, vibration and odor mitigation is in on-going.

·      Masonry infill will continue.

·      Site fence to be installed to encompass the sidewalk on Binney Street.

Welcome to the 50 Rogers Street outreach site!


Thanks for visiting our new website. We're using this interface to help you follow the construction process for 50 Rogers Street.

Click the Follow button to receive news via email, and visit the Comments tab to share questions and thoughts with us. We'll respond as soon as we can.