The first residents at Spoke have moved in! The City of Atlanta has issued a Temporary Certificate of Occupancy (TCO) for the southern half of the building as well as both levels of the parking garage. A temporary leasing office has been in place at the southwest corner (LaFrance Street/Whitefoord Avenue) since late last year. The northern half of the building is in full finishes mode. The entire 224-unit apartment building with amenities is still on track for substantial completion in April.  

Construction Update

Construction activities remain in full swing at the Edgewood/Candler Park TOD site. The western half of the building is in full finishes mode with the installation of cabinets, countertops, flooring and fixtures occurring daily. On the eastern half of the building, the mechanical, electrical and plumbing rough-ins are finishing up and drywall installation is underway. The development remains on track with the completion of the 224-unit apartment building in sections starting with the western half by late January 2018. The temporary leasing office will open next week. Visit www.spokeatl.com for leasing information.  


Construction Update

The stage of construction has reached an exciting milestone with the western half of the 224-unit apartment building in full finishes mode with cabinets, countertops, tile and MEP fixtures underway. On the eastern half of the apartment building, framing is near completion. The 224-unit apartment building remains on track for completion in sections by late January 2018. A temporary leasing center will open in late fall of 2017.

Construction Update

Construction of the Edgewood/Candler Park TOD is rapidly advancing with the completion of the 224-unit apartment building in sections to begin in January 2018. Wood framing is underway on the eastern half of the development site as the installation of insulation and drywall is gearing up on the western half of the site. Interior finishes will begin in a few months. Plans are moving forward on the temporary leasing office to open in Fall of 2017.

Construction Update

Construction of the Edgewood/Candler Park TOD is progressing very well. The structural concrete is substantially complete and wood framing is in full swing with topping out projected to occur for half the building within the next 30 days. The 224-unit apartment building is on track for completion in sections around December 2017. The temporary leasing center is set to open in fall of 2017.  

Concrete Pour Rescheduled for April 29th

Due to upcoming weather conditions, the early morning concrete pour that was originally scheduled for April 28th has been moved to April 29th. See Capstone Building Corp.’s notification letter for more details.  

Overnight Concrete Pour Scheduled for April 28th

For additional details, please see Capstone Building Corp.'s notification letter.

Overnight Concrete Pour Rescheduled for April 8th

Due to the recent severe weather, the next overnight concrete pour has been rescheduled for Saturday, April 8th. For more details, please see Capstone Building Corp.'s notification letter.

Overnight Concrete Pour Rescheduled for April 7th

For more details, please see Capstone Buildings Corp.'s notification letter.

Overnight Concrete Pour on April 4th

For more details, please see Capstone Building Corp.'s notification letter.

Construction Update

Construction is progressing very well for the Edgewood/Candler Park Station TOD. The project completion of early 2018 is currently slightly ahead of schedule. The elevator shafts are clearly visible as well as the start of wall framing. The podium parking deck concrete pours are nearing completion with the last podium concrete pour projected to wrap-up by mid-April.  

Overnight Concrete Pour Rescheduled for Feb. 23rd

For more details, please see Capstone Building Corp.'s notification letter.

Spoke Update at ONE Upcoming Community Meeting

Columbia Ventures will provide an update on Spoke, the Edgewood/Candler Park TOD at the next Organized Neighbors of Edgewood (ONE) community meeting at Antioch East Baptist Church.

Date: February 20, 2017

Location: Antioch East Baptist Church (1233 Hardee St NE, Atlanta, GA 30307)

Time: 6:30pm

Construction Update

The development site has been cleared and graded, and all underground utilities and infrastructure are in place with the exception of the storm detention. The three tier concrete podium is near completion and wood framing is set to begin in a few weeks. Columbia Ventures, MARTA’s development partner, is on track to complete the 224-unit apartment building in sections starting in December 2017. The leasing center will open in the fall.  

Overnight Concrete Pour on February 10th

Capstone Building Corp. intends to have an early concrete pour on Friday, February 10th at 12:00am. The concrete trucks and pump trucks will be running throughout the night until approximately 9:00am. We apologize for any inconvenience and appreciate the community’s patience through the Edgewood/Candler Park TOD construction process.

Closing and Groundbreaking

We are excited to share that the Edgewood/Candler Park TOD closed on July 12 and site work has begun. Buses have been rerouted through the project and a new pedestrian entrance has been established to the east of Lowery Street. 

Columbia Ventures has named the project Spoke (spokeatl.com), a nod to the site’s unique location and the connectivity it will afford its residents. About a third of the existing south parking lot on La France Street will undergo redevelopment in the first phase, delivering 224 apartment homes in early 2018. Construction will also begin early next year on a neighborhood park with a local restaurant and a performing arts center for Moving in the Spirit, a local youth development organization. The last phase of the project, on the easternmost portion of the lot, will include additional housing and commercial users as well as MARTA patron replacement parking. 

Welcome to our Project Site!

Thank you for visiting our project information site. We're using this platform to help you easily find project plans, documents, and changes in the project status.

Follow the project to receive email notifications about new updates and visit the Community Forum to share your questions, comments, and ideas with us.