Frost Terrace

Cambridge, MA
Official construction updates on the redevelopment of 1791 Mass Ave and 1 & 2 Frost Terrace into affordable housing in Porter Sq, Cambridge.
Developer
Phase
Construction
affordable housing
40 Units
  • Created by Corey Niemann from the Noun Project>

    Anticipated Construction Completion

    Construction is expected to be completed in the Fall of 2020.

  • Created by ProSymbols from the Noun Project

    Siding Installation

    Anticipated End Date: 1/28/20

  • Created by ProSymbols from the Noun Project

    Site Work and Landscaping

    Anticipated End Date: 10/30/20

  • Created by ProSymbols from the Noun Project

    Steel Stair Installation

    Anticipated End Date: 11/20/20

  • Created by ProSymbols from the Noun Project

    Interior Work

    Anticipated End Date: 2/26/20

  • Created by ProSymbols from the Noun Project

    Window Installation

    Anticipated End Date: 3/25/20

  • Created by ProSymbols from the Noun Project

    Utility Work

    Anticipated End Date: 12/10/19

  • Created by ProSymbols from the Noun Project

    Structural Framing

    Anticipated End Date: 1/29/20

  • Created by ProSymbols from the Noun Project

    Site Clearing

    Anticipated End Date: 8/9/19

  • Created by ProSymbols from the Noun Project

    Excavation Work

    Anticipated End Date: 9/2/19

  • Created by ProSymbols from the Noun Project

    Demolition of Existing Site