Update #3

Construction Update: October, 2, 2019

If you spend much time in Porter Square, you've probably noticed the growing construction activity at Frost Terrace! We're excited to share with you the progress underway.

Over the next TWO WEEKS the following construction activities will take place:

  • Relocation of the 1791 Mass Ave. Building.
  • Form and pour foundation for 1791 Mass Ave. Building.
  • Excavate, remove soils, and prep for footings for the 1789 Mass Ave Building.

If you'd like to see a detailed construction timeline, scroll to the bottom of the "Info" page to access the master schedule and 3-week look ahead. To see more photos of the site conditions, click the "Photos" tab. We will be uploading construction progress photos weekly!

We appreciate our neighbors' patience with the ongoing construction and are working hard to minimize any disruptions. Should you have any questions or concerns regarding the ongoing work please post a comment here; and we'll respond as soon as we can.