Construction Update: June 5 - 17, 2017

MBTA Plaza

On Monday, June 12th, the pedestrian plaza connecting Carleton Street to the inbound Kendall Square MBTA Station on Main Street is scheduled to close fully to allow construction of an underground garage in this area. The path in this area was recently narrowed and will now fully close for the duration of the project. Pedestrians will be guided to seek alternate paths to and from the station using Ames Street, Dock Street, or Wadsworth Street.

Access to the MBTA station and elevator will remain open and accessible on the Main Street side of the station throughout this work.

Carleton Street will remain open to vehicular traffic from Amherst Street to the Medical Parking Lot.

 

Construction Update June 5th through Saturday June 17th

 

Street and Sidewalk Impacts:

Wadsworth St. –The street will remain closed between Amherst Street and Memorial Drive (between Buildings E51 and E52) 24 hours a day to vehicular traffic. Vehicles on Memorial Drive should access the Kendall Square area via Ames Street. For the duration of excavation and installation, Wadsworth Street will remain closed as a location for equipment set up and staging. (W1).

Carleton St – The street will remain closed to all traffic except for the Medical Building Parking Lot and emergency services. Utility work on the street includes water line repairs (C1) and electrical duct bank installation (C2).

The stair repair for the MIT Medical Building (C3) will begin the week of June 12th.

Amherst St. - Forced Sanitary installation (A1) will continue on the south (100 Memorial Drive) side of the street. Chilled Water piping installation (A2) may begin. Pedestrian detours will be in place as the work progresses down the street.

Eversource will continue to install gas services (A3) towards Ames Street beyond Carleton Street.

 

 General Construction Update -

 Work continues on the Kendall Garage behind 292 Main (E38), 290 Main (E39), and 238 Main (E48). This includes -

  • Slurry Wall (Support of the Excavation) installation.
  • Daily deliveries of steel and concrete.
  • Daily trucking to remove material from the site.

Steel will continue to be installed in E38 / E39.

Scaffolding will be installed on the face of E38 / E39 buildings.

Site work will continue on site 5 (behind Cambridge Trust)

Interior demolition will continue in the Cambridge Trust Building

Police details will be utilized throughout the project area to assist with pedestrian and vehicular traffic.