Update #79

Construction Update March 29 - april 12

Street and Sidewalk Impacts

Wadsworth Street – Phase 2 Roadway Conditions into April 2019

  • Access to Wadsworth Street from Main Street is closed to all traffic. (W1) The Sloan and Eastgate lot entrance is closed at Wadsworth Street through this phase.
  • Construction vehicles and equipment will continue to be set up and operate in this area and at the intersection with Amherst Street.
  • The noisiest work will come from the intermittent use of vacuum trucks.
  • Sanitary pipe installation continues near Main Street.
  • Walkways will be maintained and located as required around construction work zones.
  • Bicycles must be walked on the shared walkway.
  • The walkway onto Wadsworth Street from Main Street has shifted back to the East side with Eversource Gas work moving north towards Main Street. Crews will remove the jersey/wall barriers to create the work zone moving from Amherst to Main and replace with chain link fencing.

Main Street

  • Construction access at Gate 1, located on Hayward Street off Main Street, continues to be a major entrance into the project for excavation and concrete
  • The covered pedestrian walkway between the MBTA headhouse and Dock Street at the Kendall Hotel has been restored. 

Amherst Street 

  • Installation of a new Eversource gas pipe is complete. Eversource gas connections to the new pipe are being completed. (A1)
  • Amherst Street remains one-way from Wadsworth Street toward Ames Street. Only police directed construction vehicles will have two-way access from Ames Street.
  • Hayward Street, from Main Street to Amherst Street, remains closed for vehicle and pedestrian traffic.

General Construction Update

Kendall Garage:

  • Reinforcement steel, concrete operations, and excavation will continue with trucking in and out of Gates 1,4,5,6, and 7 at Amherst, Hayward, Carleton, and Main Streets.
  • Finishing of concrete underground will require extended hours on days of placements.

Site 3:

  • Reinforcement steel, concrete operations and excavation will continue with trucking in and out of Gates 1,4,5, 6, and 7 at Amherst, Hayward, Carleton, and Main Streets.

Site 4:

  • E38 interior and exterior renovation activities will continue and will be serviced from Gate 11 (Between the MBTA and E38).
  • E39 slab on deck installation has started and is being serviced from Carleton Street and Hayward Street. Finishing of the concrete slab will require extended site hours on days of placements.
  • Concrete for the 29th floor is in progress and is supported from Carleton Street and Hayward Street.
  • Mega panel installation continues on 2nd shift, from 6:00 PM to midnight.

Site 5:

  • Daily deliveries of steel and concrete and removal of materials will take place from Amherst Street to Carleton Street or in and out through two Main Street gates.
  • Steel installation continues up to the 19th floor.

Police details will be utilized throughout the project area to assist with pedestrian and vehicular traffic.

Large equipment will be removed and brought back to the site daily. This activity may occur after hours but no disruptions are expected.  

Saturday Work – General construction activities will continue on Saturdays. Work will occur within the City of Cambridge allowable work hours, 9:00 am to 6:00 pm