Update #16

Construction Update 8/26/2022

Saturday 8/27/2022

Quinn Iron will have a crane setup in the Rogers Courtyard to hoist steel up to the roof of the Mechanical Penthouse. The crane will be setup at 9am per the City of Cambridge noise ordinance. Eversource Gas will continue to install the new gas service into the building. They will be working along Rogers Street and continue into the Charles Park Property. There are no lane closures required for Eversource to perform their work. Commodore Builders will be working subcontractors trades inside of the building.


Please see the two- week construction look ahead schedule for the week beginning: 8/29/22 at Charles Park in Cambridge, MA. 

 

Week of 8/29/22 – 9/2/22 

  • Select Demo will continue to remove demolition debris utilizing the loading dock off of Rogers Street. This work will continue all week. 
  • Select Demo will remove demolition debris from the building using their telehandler (mini crane). The telehandler will reach up into the loading areas on each of the floors of the building and will remove debris into the dumpsters in the courtyard lay down area. This work will continue all week. 

·    Manganaro Drywall will continue to receive deliveries of drywall framing and sheathing in the Rogers Courtyard. Installaiton of exterior sheathing will continue at the perimeter of the Rogers mechanical penthouse.

  • TG Gallagher will continue to receive deliveries of pipe and mechanical equipment through the Rogers Courtyard.
  •  All other deliveries will continue into the Rogers Courtyard to continue to load the building with materials

  

IMPORTANT NOTE: There is no 'off hours' crane pick schedule for 8/30 at 3am. This work is being resequenced with other work that will occur on the property.


Logistics / Impact: 

  • There will be increased truck traffic on Rogers Street with trucks accessing the loading dock and the courtyard lay down area for deliveries and dumpster swaps. 
  • There will be regular periods of traffic stoppage while trucks pull in and pull out of the site. 

  

Working Hours: 

Work will occur on site from 7:00am – 6:00pm (Per the City of Cambridge Construction noise ordinance). After hours work may occur if approved with a ‘off hours’ work permit. 

Please see the attached link for more information regarding the City of Cambridge noise ordinance. Please scroll down to construction for the specific information relating to construction:  https://www.cambridgema.gov/services/noiseordinanceinformation 

  

Upcoming Work: (Week Of 09/05/22) 

·      Demolition debris removal – continued from week of 8/29

·      Steel deliveries - continued from week of 8/29

·       Drywall framing and sheathing deliveries - continued from week of 8/29

·       Mechanical pipe deliveries - continued from week of 8/29

 

Outside Contractors / City of Cambridge Work: 

Please note that outside contractors such as Eversource, National Grid, Comcast, Verizon, the City of Cambridge, etc. will require access to their infrastructure in and around the area of Charles Park. We are not always privy to this work, nor do we control this work, but we will do our best to coordinate our work the best we can with the work that is going on in the neighborhood. 

  

Outside Deliveries: 

Please note that outside delivery services such as UPS, FedEx, Amazon, Uber, Lyft, Grub Hub, Door Dash, trash services, etc. will continue to make their deliveries to the area surrounding Charles Park. We do not control those providers, but we hope that they will respect the construction control (barriers and signage) along Rogers Street. If not, they will be reported to the City of Cambridge.