• Phase IV Kickoff

    Phase IV - Plan Adoption and Finalization begins

  • Phase III Kickoff

    Phase III - How Should Winchester Achieve Its Vision and Goals begins

  • Select Board Public Presentation #3

    The project team will present draft community vision statement and goals to a joint meeting of the Select Board and Planning Board. This will conclude Phase II.

  • Master Plan Steering Committee (MPSC)

    The project team will meet with the steering committee to review and discuss the first draft of the community vision and goals.

  • Community Vision Statement and Goals Drafted

    The team submitted a first draft of the community vision statement and goals report to the MPSC.

  • Spring Outreach

    The project team will attend a number of community events and hold a number of tabling events at community establishments and institutions.

  • Master Plan Steering Committee (MPSC)

    The project team will meet with the MPSC to review the findings from the public forum and plan additional outreach throughout the spring.

  • Public Forum

  • Select Board Public Presentation #2

    The project team presented a final draft of the existing conditions analysis to the Select Board.

  • Master Plan Steering Committee (MPSC) Meeting

    The project team will meet with the MPSC to kickoff Phase II of the project and to develop a community outreach and engagement plan for Spring 2019.

  • Existing Conditions Report Drafted

    The team submitted a first draft of the Existing Conditions report to the MPSC.

  • Master Plan Steering Committee (MPSC) Meeting

    The project team met with the MPSC to review findings from the focus group, stakeholder interviews, and MAPC community survey.

    Summary - Community Survey
  • Focus Groups and Stakeholder Interviews

    The project team held six focus groups and multiple interviews to gain a better understanding of key issues and opportunities and to help focus the direction of data collection and analysis of existing conditions

    Summary - Focus Groups
  • Select Board Public Presentation #1

    The project team presented the project schedule and introduced the team at a Select Board meeting.

  • Project Kickoff Meeting and Community Tour

    The project team toured Winchester with the Town Planner and Planning Board Chair, and met with the Master Plan Steering Committee.